See All 분석 및 시뮬레이션 소프트웨어 See All DAQ 소프트웨어 See All 드라이버 및 API See All 유틸리티 See All 진동 제어 See All 고정밀 및 보정 시스템 See All DAQ 시스템 See All S&V 핸드헬드 장치 See All 산업용 전자 제품 See All 전력 분석기 See All S&V 시그널 컨디셔너 See All 음향 트랜스듀서 See All 전류 및 전압 센서 See All 변위 센서 See All 힘 센서 See All 로드셀 See All 멀티 컴포넌트 센서 See All 압력 센서 See All 스트레인 센서 See All 스트레인 게이지 See All 온도 센서 See All 기울기 센서 See All 토크 센서 See All 진동 트랜스듀서 See All 진동 테스트 장비용 액세서리 See All 진동 컨트롤러 See All 측정 여기기 See All 모달 익사이터 See All 파워 앰프 See All LDS 셰이커 시스템 See All 테스트 솔루션 See All 액추에이터 See All 내연 엔진 See All 내구성 See All eDrive See All 생산 테스트 센서 See All 변속기 및 기어박스 See All 터보 충전기

Reliability Phase Diagrams

What are reliability phase diagrams?

 

Reliability Phase Diagrams, or RPDs, can be thought of as an extension of the Reliability Block Diagram (RBD) approach. RPDs graphically describe the sequence of different operational and/or maintenance phases experienced by a system. This means that, unlike an RBD which is limited to systems with fixed configurations, RPDs can be used to represent complex systems that may change over time. The change may be in the reliability configurations (i.e. the RBD) and/or other properties, such as the availability of resources or throughput properties. In this article, we will use ReliaSoft BlockSim to illustrate the use of reliability phase diagrams to study a complex system.

In complex systems, each stage during a mission can be represented by a phase block. The properties of the phase block are inherited from an RBD corresponding to the system's reliability configuration in that phase, along with any associated resources of the system during that time. A reliability phase diagram is then a series of such phase blocks connected in chronological order.

Using BlockSim for phase analysis with complex diagrams

 

Consider a process where a robot manipulator is used. Because the system operates in a remote location and stopping the operation is costly, individual components that fail but do not cause a system failure are not repaired immediately. The failed components are repaired only during the scheduled yearly maintenance of the entire operation. System failures, however, are given immediate attention, and these repairs are costly, time-consuming and incur additional warranty costs per hour of downtime. The robot manipulator is warranted for 5 years. The goal of the analysis is to determine the warranty costs incurred by the system. In order to accomplish this, three metrics are of interest: the expected number of failures of the system, the system downtime associated with unplanned system failures and the expected number of component replacements during the yearly maintenance.

Reliability phase diagram

 

Representing the robot system with a single RBD would result in limitations. For example, a corrective repair of a component that is due to a system failure needs to be handled differently than a corrective repair performed during the yearly maintenance because they incur different costs. Therefore, the following RPD will be used.

Figure 1 shows the properties of each phase.
 
Figure 1: Phase properties for the robot manipulator system RPD

By using two phases to represent the system, we segregate the results obtained from different stages (normal vs. yearly maintenance) as well as any input variations. The normal operation phase represents the system while in operation. In this phase, blocks that fail but do not bring down the system are not repaired upon failure but remain down until the scheduled yearly maintenance. However, the failure of a block that causes a system failure will result in the repair of that block as well as a repair of all other failed components. The Normal Operation phase inherits its properties from an RBD representing the system (Figure 2). Meanwhile, the Scheduled Yearly Maintenance phase represents the portion of the mission time when the system is brought down each year so that maintenance actions can be performed on some or all of its components. In BlockSim, a maintenance phase block is defined by, and linked to, a maintenance template. This template is a list of the specific components (blocks) that are designated to undergo inspection, repair or replacement actions during the maintenance phase (Figure 3).

Robot manipulator failure modes
Jam subdiagram
Brake subdiagram
Watchdog subdiagram
Comm subdiagram
Mechanical failure subdiagram
Figure 2: Robot manipulator system diagram and subdiagrams
Figure 3: Maintenance template associated with the Scheduled Yearly Maintenance phase block

Analysis

 

Table 1 gives the failure and repair inputs of the system.

Block name Failure distribution
normal operation
(in days)
Repair distribution
normal operation
(in days)
Repair distribution
yearly maintenance
(in days)
JF WBL(Beta=4, Eta=6000) EXP(Mean=12) EXP(Mean=3)
KRF WBL(Beta=2, Eta=7000) EXP(Mean=12) EXP(Mean=4)
COM EXP(Mean=5000) EXP(Mean=16) EXP(Mean=4)
EStop EXP(Mean=4000) EXP(Mean=14) EXP(Mean=2)
MSF WBL(Beta=3, Eta=10000) EXP(Mean=13) EXP(Mean=4)
RCF EXP(Mean=5000) EXP(Mean=14) EXP(Mean=5)
Primary brake Cold standby, active distribution:
WBL(Beta=2, Eta=1000)
EXP(Mean=10) EXP(Mean=5)
Secondary brake Cold standby, active distribution:
WBL(Beta=2, Eta=1000)
EXP(Mean=10) EXP(Mean=5)
Processor I Load sharing, WBL-IPL:
Beta=1.5, K=2.38E-4, n=1.32)
EXP(Mean=9) EXP(Mean=2)
Processor II Load sharing, WBL-IPL:
(Beta=1.5, K=2.38E-4, n=1.32)
EXP(Mean=9) EXP(Mean=2)
Sensor EXP(Mean=5000) EXP(Mean=9) EXP(Mean=2)
Primary PN EXP(Mean=5000) EXP(Mean=12) EXP(Mean=3)
Secondary PN EXP(Mean=5000) EXP(Mean=12) EXP(Mean=3)
Third PN EXP(Mean=5000) EXP(Mean=12) EXP(Mean=3)
Fourth PN EXP(Mean=5000) EXP(Mean=12) EXP(Mean=3)
Other EXP(Mean=100000) EXP(Mean=15) EXP(Mean=3)
Table 1: Failure and repair properties
We can now run a simulation for the mission time of interest (5 years or 1825 days).
 
Figure 4: Simulation settings
BlockSim provides multiple results at the overall mission level, as well as at the phase level. The results of interest are highlighted in Figures 5 and 6.
 
Figure 5: The expected number of failures and the component downtime associated with system failures
Figure 6: The expected number of component replacements during yearly maintenance

Conclusions

 

From the results we can conclude that the majority of the time (89.4%) our system should be running at 100% capacity and that after the 10-year period there is about a 5.3% chance that the system will degrade to a point from which it cannot be restored (the salvage state).